AUgust 2024 update
The month of August involves forming of levels 12 & 13 and preparation of upper floors.
Formwork remains the primary activity as we continue to build the structure of the building.
Residents are asked to be mindful of the ongoing concrete, rebar, and equipment deliveries to the project.
Please exercise caution and be aware of traffic.