DEcember 2023 update

 

The month of December involves the completion of our parking garage including the Ground Level. Formwork remains the primary activity as we continue to build the structure of the building. Residents are asked to be mindful of the ongoing concrete and rebar deliveries along Mutual St. Please exercise caution and be aware of traffic.