March 2025

  • The month of March involves forming of levels 30 to 32.

  • Removal of CTT Crane and installation of CDK crane for preparation of upper floors.  

  • Formwork remains the primary activity as we continue to build the structure of the building.

  • Residents are asked to be mindful of the ongoing concrete, rebar, and equipment deliveries to the project.

  • Please exercise caution and be aware of traffic.